EXT 1/31/25 for 1 year bond. MD*
Post Revision # 14: Temporary access/egress out of the east side of Block 6 to 124th Ave. NE during completion of the 124th Ave. NE frontage work.
Post Revision # 10: Close one lane on 124th Ave. for taking deliveries and staging trucks.
Post Revision # 9: Close the westbound of NE Spring Blvd. to remove the conveyor.
Post Revision # 8: Close both westbound lanes on Spring Blvd. for the erection of a tower crane and bringing in a mobile crane.
Post Revision # 7: Construction of temporary concrete pad along NE Spring Blvd for a construction conveyer belt, and the associated demolition and fence adjustments.
Post Revision # 6: Traffic Control Plan from Ness Campbell Crane for installation of conveyor.
Post Revision # 3: Remove portion of the existing sidewalk and planter strip for the construction of temporary access route for hauling.
Post Revision # 1: Alternate trucking route with a traffic loop off of 124th Ave. NE
Haul route only for the development Block 6 office building. Subject to Clearing and Grading Permit # 20 105514 GD