Post Revision # 5: Proposed new location of the Mailbox Cluster.
Post Revision # 4: ROW improvements includes the reconstruction of the Curb and Gutter and Sidewalk along Kamper Road and 140th Ave. SE Per COB Std. drawing SW-110-1 and Std. drawing RC-240-1; Construct 16’ Wide driveway along Kamber Road and 2-20’ wide driveways along 140th Ave. SE as shown on Sheets F1-01 & F1-02; Storm drain connections along Kamber Road and 140th Ave. SE as shown on sheet RS-01; 6” Side Sewer connections as shown on sheet SW-01; includes water main connection; Asphalt Pavement restorations; and landscape as illustrated on the landscape plans, as approved on the Clearing and Grading permit # 20 110074 GD
Haul route only for the development of the Cook Plat Infrastructure. Work in the Right of Way subject to approved Plat Infrastructure permit # 20 110074 GE.