Post Revision # 33: Traffic control plans for Midblock Crossing and Grind and Overlay.
Post Revision #31: TCP for mid-block crossing
Post Revision # 22: Setup traffic control on NE 4th St. and the sidewalk for the installation of communication line in the private property at Key Bank Pavilion. As approved under permit # 20 123445 GD.
Post Revision # 20: Full roadway closure of 106th Ave. NE and partial roadway closure of NE 4th St. for a Mat foundation pours.
Post Revision # 19: Setup traffic control at the intersection of NE 4th St. and 106th Ave. NE for the install of storm drain as approved under permit # 20-123446 UE.
Post Revision # 18: Water line extension & 106th Ave. NE interim channelization as approved on Post issuance # 9.
Post Revision # 16: Temporary roadway closure for tower crane erection.
Post Revision # 15: Temporary pedestrian protection canopy on 4th street sidewalk for the duration of construction.
Post Revision # 14: Updated interim channelization plans reflecting corrected taper ratio at the North and South ends
Post Revision # 13: Revised Interim Channelization Plans, and setup traffic control on 106th Ave. NE for setting of tower crane base and excavation conveyor.
Post Revision # 11: Reserve two City of Bellevue parking spaces on 2nd Ave. for AC Marriott on 106th Pl. NE for shuttle load & unload to alleviate alley traffic congestion because of the nearby construction activities.
Post Revision # 7&10: Shoring/tie-back in the ROW as approved under Shoring Permit # 20 104041 BV PR#1.
Post Revision # 8: Approved Traffic Control Plans for the Interim Channelization Plans.
Post Revision # 6: Approved Interim Channelization Plans.
Post Revision # 5: Traffic Control Plan for CCTV of Storm and Sewer on 4th St.
Post Revision # 2: Setup traffic Control on 106th Ave. NE for the building demolition.
Post Revision # 1: Additional potholing on 106th Ave. NE & NE 4th St.
Potholing along the sidewalk to locate the shared communication duct-bank