Ext. 8/11/23 CR. EXT 1/3/23 KB. EXT 7/29/22 KB. EXT 1/7/22 KB. EXT 6/1/21 KB. 6.18.20
8/11/23 - Work proposed to completed ADA compliant driveway approach and sidewalk ramps.
New Issuance Date- One at a time occupying the E and W bound lanes of NE 20th St to replace 2" and 4" DuPont main installed on 793-351. Replace 4" PE main in NE 20th St from 1270' E to 1935' E of c/L of 140th Ave Ne. Replace 2" PE main at 1935' of 140th Ave NE from 13' S to 632' N of C/L of NE 20th St and at 633' N of C/L of NE 20th St from 1933' E to 1715' E of C/L of 140th Ave NE (services 14506 - 14510 NE 20th St) Total disturbance will be 822 cubic yards. Method of install is trenching.
11.20.19 - Permit Approval to access manholes within the traveled lanes and sidewalks. No ground disturbance at this time.
GROUND DISTURBANCE WORK ASSOCCIATED WITH THE MAIN LINE INSTALL NOT APPROVED AT THIS TIME: