As requested by the inspector. I have extended until Apr 30, 2024, to complete the work as required. MW
Post Revision # 22: Replacement of the C curb on NE 10th St.
Post Revision # 21: Setup traffic control for the installation of traffic loops and striping on 106th Ave. NE
Post Revision # 19: Concrete panel and curb replacement along NE 10th St.
Post Revision # 17: Tower Crane Removal.
Post Revision # 16: Provide the composite plans for franchise telecom utility joint trench
Post Revision # 15: Taking of an extra lane temporarily during to allow extra room from the delivery trucks
Post Revision # 12: Traffic Control Plan to close the curb lane on NE 10th St. for delivery and steel erection.
Post Revision # 10: Traffic Control Plan to for To Remove the conveyor from the hole.
Post Revision # 8&9: Traffic Control Plan to Pothole a future light pole per COB request on 106th St East lane.
Post Revision # 5,6,&7: Employee parking plans, Pothholing on 106th Ave. NE and Right of Way Lease Plan.
Post Revision # 4: Right of Way Lease Plan, and closure of WB NE 10th St. for crane erection.
Post Revision # 2: Potholing on NE 10th St. Subject to an approved Clearing & Grading Permit # 18 131810 GD
Post Revision # 1: Haul Route for the excavation Subject to Clearing & Grading Permit # 18 105116 GD
Intercept the storm sewer at 106th Ave. & the demolition of the two existing buildings to the slab levels.
Subject to an approved Clearing & Grading Permit # 18 131810 GD