Post Revision # 13: Setup traffic control on 103rd Ave. NE for the underground utility work on as approved under the utility permit # 18 104373 UE, using previously approved traffic control plans # TCP-5 & TCP-6.
Post Revision # 12: 2023 Lease adjustment rate.
Post Revision # 11: Interim Channelization Plans.
Post Revision # 8&9: Setup traffic control on NE 10th St. for Mobile crane and close NE 10th St. for crane erection.
Post Revision # 7: Phase 2 Potholing at East Side of 103rd Ave. NE & ROW lease on 103rd Ave. NE for job site trailer (8' WIDE PARKING LANE + 4' OFSIDEWALK PLANTING STRIP)
Post Revision # 3& 4: Revised traffic control plans for the mass excavations.
Post Revision # 2: Leasing Sidewalk only. Pedestrian detour as approved on TCP-1
Post Revision # 1: Set up traffic Control on NE 10th St for the mass excavations; revised hauling route.
Haul route for the development of the Mirador Phase II Condominium tower.
Work in ROW Subject to an approved Clear and Grade Permit