Extended to 11/30/20 by wz. PSE didn't power City street light.
MOD 3/24/20 BMW, EXT 1/31/20 kb, EXT 12/10/19 kb. Remove existing poles P02 through P07 located on the west side of 150th Ave SE and install new poles through P09 through P13 on the east side of 150th Ave SE. The project will require the job to completed in two phases, the first phase will to remove poles P02 and P03 and relocate to locations P09 and P10 in order to give the city of Bellevue room to install new wall on the east side of the road while starting construction of wall on the southwest corner of 150th Ave SE. When the wall is completed on the east side of the road, PSE will relocate all remaining poles to the east side to make room for the city of Bellevue to complete construction on the west side of the road. See attached work sketch.