EXT FOR FINAL PER KH 11/5/20 KB. Revision # 10 Traffic Control Plans for the asphalt restoration.
Revision # 9 construct new Companion Ramp on the north side of NE 11th St. and replace damaged sidewalk.
Revision # 8 Abandon existing utilities on NE 10th St.
Revision # 7 Installation of the signal poles located on NE 10th Street, and the staging for a mobile crane to set windows on our sports court.
Revision # 6 Closure of the south bound lanes of 112th Ave. NE for the sewer connection as approved on the
Clearing and Grading permit.
Revision # 5 Left lane closure on NE 10th f 112th Ave. NE for the storm water connection as approved on the Clearing and Grading permit.
Revision # 4, Left lane closure of 112th Ave. NE for Forming Table Extraction ustlizing TCP-05
Revision # 2, Roadway closure for the crane erection. This scope of work will take 2 days. TCP-03
Revision # 1, Added early stage of demolishing truck loading zone and route. TCP-02
Hall Route only for the redevelopment of site to construct high-rise mixed use residential apartment building with 258 units and below grade parking for 400 cars.